Field Cases

Oilfield gathering station — crude oil line

Field Reality

A crude oil line at an oilfield gathering station had a perforation leak. A clamp and plastic pad had already been fitted as a temporary measure and had begun leaking again quickly. The Field that DendroSeal was asked to look at was therefore not a bare pipe: it was a pipe with a failed prior repair still on it, and dark liquid running from underneath it.

Dark liquid leaking from a clamp and plastic-pad arrangement on a vertical steel pipe.
Active leakage from beneath the prior clamp and pad.
Wider view of the prior metal clamp arrangement on the DN100 line.
The wider existing condition: the prior clamp arrangement in place on the line.

Key verified Field facts

Medium
Crude oil operator-reported service
Pressure
10 bar operator-reported
Asset
DN100 steel pipe at a gathering station operator-reported
Geometry
Vertical run carrying a previously fitted clamp and plastic pad observed in the Field record
Field condition
Perforation leak; the prior clamp and plastic pad re-leaked quickly operator-reported and visible in the Field record
Dominant hazard / constraint
Continuing crude oil release from beneath a failed temporary repair observed in the Field record

Resulting ISB

No completed-state record is published for this Field. The Field Reality above is what the record supports, and nothing has been added to make the sequence look finished.

Case boundary

This Case records one unique Field Reality. It is not a construction instruction and not a template. A Solution developed for one Field must not be copied into another Field without new DendroSeal Understanding.